(a) A license will be issued, authorizing the whole or any part of service requested, if the Commission finds that:
(1) The applicant is
fit, willing and able to properly perform the service proposed in conformance
with applicable provisions of 66 Pa.C.S. (relating to the Public Utility Code)
and the lawful Commission orders and regulations, specifically including
Chapter 56 (relating to standards and billing practices for residential utility
service).
(2) The proposed service
is consistent with the public interest and the policy declared in the act (See
section 2208(b) of the act (relating to requirements for natural gas
suppliers)).
(b) Completed applications, with all supporting documentation, including any documentation or clarifying information requested by Commission staff, if unprotested, will be processed within 45 days after acceptance by the Commission. If the application is not processed within the time period, the application will be deemed approved. The review period may be extended for a reasonable period of time by Secretarial Letter.
Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.