Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 62 - NATURAL GAS SUPPLY CUSTOMER CHOICE
Subchapter D - LICENSING REQUIREMENTS FOR NATURAL GAS SUPPLIERS
Section 62.105 - Change in organizational structure or operational status
Current through Register Vol. 54, No. 38, September 21, 2024
(a) The applicant is under a duty to inform the Commission of a material change in the information provided in the application during the pendency of the application, or while the licensee is operating in this Commonwealth.
(b) A material change in the organizational structure or operation that affects an applicant's or a licensee's operation in this Commonwealth shall be reported to the Commission within 30 days of the date of the change. Specifically, notification shall be given to the Commission of a change in the following:
(c) Unless directed otherwise by the Commission, the licensee does not need to file an amended application with the Commission.