Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 57 - ELECTRIC SERVICE
Subchapter N - ELECTRIC RELIABILITY STANDARDS
Section 57.194 - Distribution system reliability
Current through Register Vol. 54, No. 38, September 21, 2024
(a) An EDC shall furnish and maintain adequate, efficient, safe and reasonable service and facilities, and shall make repairs, changes, alterations, substitutions, extensions and improvements in or to the service and facilities necessary or proper for the accommodation, convenience and safety of its patrons, employees and the public. The service shall be reasonably continuous and without unreasonable interruptions or delay.
(b) An EDC shall install, maintain and operate its distribution system in conformity with the applicable requirements of the National Electrical Safety Code.
(c) An EDC shall make periodic inspections of its equipment and facilities in accordance with good practice and in a manner satisfactory to the Commission.
(d) An EDC shall strive to prevent interruptions of electric service and, when interruptions occur, restore service within the shortest reasonable time. If service must be interrupted for maintenance purposes, an EDC should, where reasonable and practicable, attempt to perform the work at a time which will cause minimal inconvenience to customers and provide notice to customers in advance of the interruption.
(e) An EDC shall design and maintain procedures to achieve the reliability performance benchmarks and minimum performance standards established by the Commission.
(f) An EDC shall develop and maintain a program for analyzing the service performance of its circuits during the course of each year.
(g) An EDC shall maintain a 5-year historical record of all known customer interruptions by category of interruption duration, including the time, duration and cause of each interruption. An EDC shall retain all records to support the reporting requirements under § 57.195 (relating to reporting requirements) for 5 years.
(h) An EDC shall take measures necessary to meet the reliability performance benchmarks and minimum performance standards established by the Commission.
The provisions of this §57.194 amended under the Public Utility Code, 66 Pa.C.S. § 501; and the Electric Generation Customer Choice and Competition Act, 66 Pa.C.S. § § 2801-2812.
This section cited in 52 Pa. Code § 57.195 (relating to reporting requirements); and 52 Pa. Code § 57.197 (relating to reliability investigations and enforcement).