Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 57 - ELECTRIC SERVICE
Subchapter M - STANDARDS FOR CHANGING A CUSTOMER'S ELECTRICITY GENERATION SUPPLIER
Section 57.174 - Time frame requirement

Universal Citation: 52 PA Code ยง 57.174

Current through Register Vol. 54, No. 38, September 21, 2024

(a) When a customer has provided the selected EGS or current EGS with oral confirmation or written authorization to select the new EGS or default service provider, consistent with electric data transfer and exchange standards, the EDC shall make the change within 3 business days of the receipt by the EDC of the electronic enrollment transaction.

(b) The EDC shall obtain a meter read to effectuate the switch of service within the time period provided for in subsection (a). In instances when the EDC does not have advanced or automated metering capability, the EDC shall obtain an actual meter read, use an estimated meter read or use a customer-provided meter read. When an estimated meter read is used, the estimated meter read shall be updated when an actual meter read is obtained.

This section cited in 52 Pa. Code § 57.180 (relating to implementation); and 52 Pa. Code § 111.6 (relating to discipline).

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.