Section 57.174 - Time frame requirement
Current through Register Vol. 54, No. 38, September 21, 2024
(a) When a customer has provided the selected EGS or current EGS with oral confirmation or written authorization to select the new EGS or default service provider, consistent with electric data transfer and exchange standards, the EDC shall make the change within 3 business days of the receipt by the EDC of the electronic enrollment transaction.
(b) The EDC shall obtain a meter read to effectuate the switch of service within the time period provided for in subsection (a). In instances when the EDC does not have advanced or automated metering capability, the EDC shall obtain an actual meter read, use an estimated meter read or use a customer-provided meter read. When an estimated meter read is used, the estimated meter read shall be updated when an actual meter read is obtained.
This section cited in 52 Pa. Code § 57.180 (relating to implementation); and 52 Pa. Code § 111.6 (relating to discipline).