Section 57.147 - Scheduled imports and exports

Universal Citation: 52 PA Code ยง 57.147

Current through Register Vol. 54, No. 38, September 21, 2024

The Annual Resource Planning Report (ARPR) shall include a forecast of scheduled imports and exports in megawatts for the EDC, the EDC's control area and appropriate regional reliability council, as defined under § 57.192 (relating to definitions).

(1) Actual data for the past year and estimated data for the ensuing 5 years shall be provided.

(2) The data shall be provided for both summer and winter seasons, the latter being the winter following the summer of the past year.

(3) A breakdown of scheduled imports and exports shall be provided including the name and type of each participating entity.

The provisions of this §57.147 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 524, 1501, 1504 and 2809.

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.