Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 57 - ELECTRIC SERVICE
Subchapter L - ANNUAL RESOURCE PLANNING REPORT
Section 57.143 - Existing and planned generating capability

Universal Citation: 52 PA Code ยง 57.143

Current through Register Vol. 54, No. 38, September 21, 2024

(a) The Annual Resource Planning Report (ARPR) shall include a description of existing generating capability, the cost of which is being recovered by the EDC in a competitive transition charge, as defined under 66 Pa.C.S. § 2803 (relating to definitions), and planned generating capability installations, changes and removals.

(1) The data shall include station name and unit number, location, date installed or to be installed, unit type, primary fuel type and fuel transportation method, summer and winter net capability in megawatts, changes in capability occurring during the past year and percent ownership share.

(2) The data shall include those facilities which are owned in whole or in part by the reporting EDC. A jointly owned unit shall be designated as such and the EDC's share of the unit shall be indicated.

(3) The data shall include actual data for the past year and estimated data for the ensuing 5 years.

(b) The ARPR shall include a description of existing generating capability and planned generating capability installations, changes and removals for the EDC's control area and appropriate regional reliability council, as defined under § 57.192 (relating to definitions).

(1) The data shall include actual data for the past year and estimated data for the ensuing 5 years.

(2) The data shall include station name and unit number, location, date installed or to be installed, unit type, primary fuel type and fuel transportation method and summer and winter net capability in megawatts.

(c) The ARPR shall include a synopsis of major occurrences where electric generation suppliers were unable to supply scheduled loads within the EDC's service territory during the previous year. The synopsis shall include the electric generation supplier's name, the amount of energy and capacity involved in megawatt-hours and megawatts, respectively, the period of time involved and other pertinent information relating to the major occurrences.

The provisions of this §57.143 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 524, 1501, 1504 and 2809.

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.