(a) When a qualified project is completed, a utility may institute a rider under 66 Pa.C.S. § 1307 (relating to sliding scale of rates; adjustments) to surcharge base rates for more timely recovery of associate costs until a time when the costs are reflected in base rates. To be eligible for this cost recovery mechanism, the utility shall comply with the following requirements:
(b) Qualified projects involving existing coal-fired units which utilize Commonwealth-mined coal for more than half of the total fuel requirements may be included in the rate base of the utility up to 50% of the undepreciated original cost of the unit involved where the project has not been completed but is expected to be completed within 2 years from the end of the test year claimed in a general rate proceeding under 66 Pa.C.S. § 1308 (relating to voluntary changes in rates).
This section cited in 52 Pa. Code § 57.123a (relating to project commencement and qualification); and 52 Pa. Code § 57.125 (relating to refunds).