Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 57 - ELECTRIC SERVICE
Subchapter J - CONSTRUCTION COSTS OF ELECTRIC GENERATING UNITS
Section 57.103 - Estimate of construction costs
Current through Register Vol. 54, No. 38, September 21, 2024
A utility required under 66 Pa.C.S. § 515(a) (relating to construction cost of electric generating units) to submit an estimate of the construction costs of electric generating units shall file the following information with the Commission as part of that estimate:
(1) An estimate of total costs.
(2) An estimate of the following costs:
The provisions of this §57.103 issued under Public Utility Code, the Public Utility Code, 66 Pa.C.S. § § 501, 515, 1301 and 1308.
This section cited in 52 Pa. Code § 53.53 (relating to information to be furnished with proposed general rate increase filings in excess of $1 million); 52 Pa. Code § 57.104 (relating to construction management program); and 52 Pa. Code § 57.105 (relating to construction monitoring program).