Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 57 - ELECTRIC SERVICE
Subchapter G - COMMISSION REVIEW OF SITING AND CONSTRUCTION OF ELECTRIC TRANSMISSION LINES
Section 57.71 - Application
Upon the application of a public utility for authorization to locate and construct a HV transmission line or any portion thereof, upon approval of the application by the Commission first had and obtained, and upon compliance with existing laws, it shall be lawful for a public utility to commence construction of the HV transmission line or portion thereof.
The provisions of this §57.71 issued under the Public Utility Code, 66 Pa.C.S. § 501.
This section cited in 52 Pa. Code § 5.14 (relating to applications requiring notice); 52 Pa. Code § 57.1 (relating to definitions); 52 Pa. Code § 57.72 (relating to form and content of application); and 52 Pa. Code § 69.3101 (relating to scope).