Current through Register Vol. 54, No. 38, September 21, 2024
(a)
General provisions. Each
utility shall purchase any energy which is made available from a qualifying
facility as required by applicable statutes and regulations. Each utility is
required to implement an all-source competitive bidding program for the
purchase of capacity and associated energy under subsection (c).
(b)
Purchases of energy
only.
(1) Energy payments in mills
per kilowatt hour shall be based upon costs in this paragraph.
(i) Energy payments will be equal to a
utility's highest cost source of energy used to supply the energy requirements
of its domestic load customers at all times. When basing contract payments to
qualifying facilities on the electric utility's future avoided cost, the
avoided energy cost shall be determined without considering the qualifying
facility about to come on line as part of the supply mix.
(ii) When the utility's energy payments for
the purchases are based on its own generation, the energy payments shall
include the costs of fuel, variable operation and maintenance expenses, and
other costs associated with that generation. The costs of units which run, but
are not economically dispatched, may be excluded by the utility in the
calculation of energy payments. The energy payments shall incorporate the costs
or savings resulting from variations in line losses from those that would have
existed in the absence of purchases from a qualifying facility.
(iii) When the qualifying facility is larger
than 5,000 kilowatts, the utility may base its energy payments on the average
cost of its last block of energy of equivalent size rather than its single
highest source of energy.
(2) Energy payments shall, at the option of
the qualifying facility, be based on actual, projected or levelized costs.
(i) The actual costs of the purchasing
utility calculated at the time of delivery, as described in paragraph
(1).
(ii) The utility's
projection-for up to 10 years or the length of the contract, whichever is
shorter-as filed with the Commission, of its energy costs, as defined in
paragraph (1), at the time the qualifying facility elects to accept this
projection.
(iii) The utility's
filed levelized projected energy costs, as determined by converting the
cumulative present value of each year's costs (projected in accordance with
subparagraph (ii)) to an annuity with the same present value, at the time the
qualifying facility elects to accept this projection. A zero risk discount
factor should be used-such as, the current rate on a United States Treasury
Bill of corresponding term. The term of levelization may be no longer than the
term of the contract or 10 years, whichever is shorter.
(iv) Contracts are required where the parties
agree to use a projection or a levelized projection as outlined in
subparagraphs (ii) and (iii). When a levelized projection of energy costs is
used, or when early year payments exceed projected avoided energy costs, for
energy-only contracts, a utility may require security from the qualifying
facility only to the extent the early year costs exceed the projection of
energy costs for those years. The security may not be a cash deposit and shall
be the least burdensome form of security among the following: an irrevocable
letter of credit; a payment bond; a fully paid noncancelable project failure
insurance policy; or corporate guarantee, lien, mortgage or deed of trust on
the facility itself. A utility may not require a qualifying facility to
reconcile payments to utility costs actually experienced during the contract
period.
(v) Contracts may be for a
period mutually agreed upon by both buyer and seller.
(3) Utilities shall purchase energy from
qualifying facilities of 500 kilowatts or greater on a uniform, time of day,
seasonal or other cost-justified basis, as determined by the utility.
(4) Qualifying facilities of less than 50
kilowatts may opt for net energy billing. Under net energy billing, the energy
taken by the qualifying facility from the purchasing utility is billed net of
the energy supplied by the qualifying facility to the purchasing utility.
However, net energy billing shall not reduce the qualified facility's minimum
bill. Utility policy for net billing is to be filed with the Commission
concurrent with other filings required in this subpart.
(5) If a qualifying facility and a utility
agree for the utility to broker the qualifying facility's power, the qualifying
facility will then be entitled to the total price received by the utility for
the energy, less any brokerage fee and other identifiable costs
incurred.
(c)
Mandatory competitive bidding for purchases of capacity and associated
energy. Jurisdictional electric utilities with annual gross intrastate
operating revenues in excess of $500 million shall establish competitive
bidding programs to obtain capacity resources. Utilities are responsible for
developing requests for proposals, and negotiating and enforcing contracts.
Small qualifying facilities (under 5 megawatts), are exempted from the
mandatory competitive bidding requirements. Utilities may purchase capacity and
associated energy from small qualifying facilities outside of an all-source
competitive bidding program. Utility sponsored DSM programs are exempt from
competitive bidding until January 2, 2000.
(1)
Sources of capacity.
(i) A
utility shall allow all sources of capacity to submit offers in a competitive
bidding program. These sources may include the utility conducting the bid,
other electric utilities, qualifying facilities, independent power producers,
exempt wholesale generators, marketers, brokers and other entities. An exempt
wholesale generator which is an affiliate or an associate of the utility
conducting the bid is subject to the prohibitions appearing at
15 U.S.C.A. §
79z-5a(k) ("Protection against abusive
affiliate transactions"). All source bidding programs are encouraged.
(ii)
Utility participation in its own
auction. A utility seeking capacity resources and companies
affiliated with the utility may participate in the capacity solicitation. All
bids are to be evaluated fairly by an independent third-party evaluator
selected by the utility. Abusive self-dealing is prohibited. A utility seeking
to participate in its own solicitation or allow its affiliate to participate in
that solicitation shall also adhere to the following requirements:
(A) Not less than 90 days prior to the filing
of a Request for Proposal (RFP) under paragraph (4), the electric utility shall
specify in writing to the Commission the names, addresses and job titles of the
utility personnel that shall be directly or indirectly involved, in any
fashion, in any of the following groups: the development of the requests for
proposals to be utilized in the competitive selection process; the ultimate
selection of successful projects or developers, or both; and the development
and formulation of the bids expected to be submitted by, or on behalf of, the
electric utility or any of its affiliates, or both. The utility shall identify
the group in which each person will work and that person's duties and
responsibilities within the group.
(B) Nothing in clause (A) limits the ability
of an electric utility to add personnel after the initial designation if:
(I) An amendment to the filing required by
clause (A) is filed with the Commission within 15 days after the new personnel
are added.
(II) Other applicable
requirements of this subparagraph have been satisfied.
(C) No one participating in the bidding
process on behalf of the utility conducting the auction may be a member of more
than one of the groups identified in clause (A).
(D) Each member of the groups specified in
clause (A) shall execute and file with the Commission within 60 days prior to
the utility's RFP filing, a written affidavit under oath acknowledging its
obligations during the competitive selection process to:
(I) Maintain in the strictest of confidence
the information, data, and the like, relating to the operators of its group and
the work-product thereof.
(II)
Refrain from communicating any information, data and the like, relating to the
operations or work-product of their group to any individuals who are members of
any other groups specified in clause (A).
(iii)
DSM projects. Electric
utilities have the option of including DSM providers and electric generation
suppliers in the same auction or in separate auctions. In auctions which
include DSM providers, the amount and type of DSM programs solicited shall be
consistent with the amount and type of DSM programs contained in the utility's
Annual Resource Planning Report filed with the Commission.
(A) Eligible DSM projects shall include
conservation as well as load management programs.
(B) DSM proposals shall be reliable and
quantifiably cost effective.
(C)
Bidders of DSM projects shall include in their bids the costs to consumers
participating in the DSM programs.
(D) Commercial or industrial DSM may not
contemplate only reductions in commercial or industrial plant output.
(E) The utility shall make known the criteria
and procedures for evaluating DSM proposals in its Request for
Proposals.
(2)
Development of the Capacity Resource Plan. A competitive
bidding process shall be responsive to the needs of the jurisdictional electric
utilities. To provide maximum flexibility in the purchase of capacity and
associated energy and DSM programs, there will be no Commission mandated
benchmarks, price factors and nonprice factors in a competitive bidding
process. Each electric utility initiating a competitive bidding process may
propose benchmarks, price factors and nonprice factors and otherwise follow
these principles:
(i) A utility's competitive
bidding program shall be an integral part of its Annual Resource Planning
Report filed under
66 Pa.C.S. §
524
(relating to data to be supplied by electric utilities) and the Commission's
regulations. A utility's Annual Resource Planning Report shall include
information on system reliability sufficient to establish a reasonable bid
block for procurement.
(ii) A
utility's need for capacity as identified in its Request for Proposal shall be
consistent with the long-term resource plans reflected in its Annual Resource
Planning Report. If the Request for Proposal is not consistent with those
long-term resource plans, the utility shall justify any differences to the
Commission before a Request for Proposal is issued.
(iii) A utility's competitive bidding program
shall be conducted at appropriate times consistent with the capacity need
reflected in the utility's Annual Resource Planning Report filings.
(iv) A utility is not required to hold an
auction if its Annual Resource Planning Report shows that it has sufficient
existing capacity to meet the needs of its customers unless the Commission
determines otherwise.
(v) Power
plant life extension programs are exempted from competitive
bidding.
(3)
Petition for Approval of Capacity Resource Plan.
(i) As provided in this subchapter, each
jurisdictional Class A utility shall file with the Commission a Petition for
Approval of its Capacity Resource Plan (petition). The petition shall be based
on each utility's then-current Annual Resource Planning Report (ARPR), filed
under §
57.141 (relating to general). The
petition shall contain the following information based upon the ARPR:
(A) The types, amounts and timing of capacity
resources, which include associated energy, that the utility plans to construct
or own, or both, in whole or in part, or which the utility plans to purchase
from unaffiliated or affiliated utilities, independent power producers, exempt
wholesale generators, qualifying facilities, marketers, brokers or other
entities.
(B) The proposed
analytical method for determining the timing, amount and duration of capacity
resources, if any, that the electric utility would purchase from unaffiliated
or affiliated utilities, independent power producers, exempt wholesale
generators, qualifying facilities, marketers, brokers or other entities over an
appropriate planning period, and the amount of capacity resources, if any, that
the electric utility should construct or own, or both, itself.
(C) The amount, type, timing, duration,
ownership and configuration of capacity resources needed over an appropriate
planning period calculated in accordance with the methodology provided in
compliance with §
57.150 (relating to evaluation and
integration of resources).
(D) The
type of information provided in compliance with §
57.150 for generation supply shall
also be provided in regard to the utility's plans to procure and implement
demand-side management programs.
(E) Other data and information requested by
the Commission to assist it in its ruling on the utility's petition.
(ii) The Commission will provide
notice of the filing of a petition to be published in the Pennsylvania
Bulletin within 30 days after the petition is filed. The notice must
contain sufficient information to advise the utility's customers, the entities
referenced in subparagraph (i), and other interested parties of the utility's
overall capacity resource needs and the operation of the utility's competitive
selection process. The notice will provide the interested parties with the
opportunity to participate in a formal Commission proceeding concerning the
petition.
(iii) Within 30 days of
the filing of a petition, the utility shall provide further notice, including
publication in newspapers of general circulation, media advertising, customer
bill inserts or other notice as the Commission reasonably believes to be
required to notify the utility's customers and interested parties of the
proceeding concerning the utility's petition.
(iv) Within 60 days after the petition is
filed, the Commission will assign the petition to the Office of Administrative
Law Judge for hearings and the issuance of a recommended decision. The
Commission will adopt a final order on the petition within 210 days after the
petition is filed. If the Commission does not enter a final order concerning
the petition within that time, the petition shall become effective as filed,
requiring no further action by the Commission or the electric
utility.
(v) A Commission order on
a petition will contain findings concerning the following:
(A) The method or approach to be used by the
electric utility to establish the amount of its capacity resource needs to be
filled by its own facilities or the facilities of unaffiliated or affiliated
utilities, independent power producers, exempt wholesale generators, qualifying
facilities, marketers, brokers or other entities over an appropriate planning
period.
(B) The appropriate
planning period for evaluating capacity resource needs, avoided costs and the
utility's actual commitment to capacity resources.
(C) The electric utility's appropriate
interconnection requirements, including physical inspection and testing
requirements, cost and payment procedures, reconciliation of actual costs to
estimates and the like
(D) The
appropriate allocation of costs for system upgrades among affected unaffiliated
or affiliated utilities, independent power producers, exempt wholesale
generators, qualifying facilities, marketers, brokers or other
entities.
(E) The timing, type and
amount of DSM programs the utility will procure and implement.
(F) The utility's methodology for evaluating
DSM programs.
(G) The utility's
proposed dispute resolution process designed to resolve in an efficient and
expeditious manner disputes associated with the competitive bidding
process.
(H) Other findings that
the Commission deems reasonable and appropriate relating to the
petition.
(vi) When a
utility's capacity resource plan, approved by Commission order under this
paragraph becomes outdated or fully implemented, or becomes inappropriate for
any reason, the utility shall file a new petition with the Commission
consistent with this paragraph. This filing shall not affect any contract
submitted under paragraph (7).
(4)
Request for Proposal
(RFP).
(i) Following the
Commission's disposition of the petition, a utility shall develop an RFP for
the purchase of capacity. The utility's RFP shall be filed with the Commission
at the appropriate time in order to meet the utility's capacity needs. A
utility's RFP shall provide accurate information about its need for capacity.
The RFP shall provide whether the utility is seeking baseload, intermediate or
peaking capacity. The RFP shall include information necessary to the
preparation of the bid proposal and the following:
(A) The size, type and timing for which the
utility anticipates contracting.
(B) The RFP shall specify any nonprice,
benchmark or other considerations, such as fuel diversity and how those factors
will be evaluated.
(C) Thresholds
that shall be met by bidders.
(D)
The criteria which will be used in evaluating the bids.
(E) Major assumptions to be used by the
utility in its bid evaluation process.
(F) Explicit instructions for preparing bids
so that bids can be evaluated on a consistent basis.
(G) The preferred general location of
additional capacity and availability of offsets or allowances.
(H) Standard power purchase and operating
agreements.
(ii) A
utility shall provide bidders with the information that would reasonably be
expected to have a bearing on the viability of a proposed project. Potential
bidders shall be able to meet with the utility to discuss the RFP and the
utility's capacity needs.
(iii)
Notice of the RFP shall be filed with the Commission, served on the Office of
Consumer Advocate, the Office of Small Business Advocate and the Pennsylvania
Energy Office and published by the Commission in the Pennsylvania
Bulletin. The notice shall include information regarding when the RFP
will be released, when bidders must submit their proposals, and when the
utility will announce the winning bidder.
(iv) The RFP shall be consistent with the
Commission's order on the utility's petition.
(v) There shall be a single due date for all
proposals, so that all proposals may be delivered to the evaluator and opened
at the same time without amendment.
(vi) Performance incentives and penalties are
encouraged to ensure efficient project operation. Performance incentives and
penalties, if used, shall be included in the RFP.
(5)
Determination of procurement
block size.
(i) The amount of
capacity or block size which the utility solicits shall be based on the
utility's incremental capacity and associated energy needs as forecast beyond
the next 5 years from the date of the utility's most recent ARPR, consistent
with the Commission's disposition of the utility's petition. Projects may be
appropriately considered in the bid assessment when their proposed in-service
date is later than the time-frame used to determine the block size.
(ii) Incremental needs refer to the level of
capacity and associated energy needs in excess of the following, less planned
utility plant retirements:
(A) Current
utility-owned generating capacity.
(B) Short-term power purchase contracts, and
commitments with other utility sources.
(C) Current signed power purchase contracts
and commitments with nonutility generators which are likely to operate, with
recognition of their likely in-service dates.
(6)
Evaluation of bids.
(i) Evaluation of bids submitted in a
competitive bidding program shall be based on the criteria identified in the
utility's RFP. All resource options competing to meet the utility's procurement
needs as determined by the Commission's disposition of the Capacity Resource
Plan shall be evaluated against each other, consistent with the requirements of
the Capacity Resource Plan and the RFP.
(ii) For auctions in which neither the
utility nor any affiliate is a participant, the utility shall objectively
evaluate all bids consistent with the RFP. If the utility or its affiliates
participate in their own bidding process, the Commission will require
independent, third-party evaluation of all bids. The Commission will closely
scrutinize all evaluations of bids.
(iii) A utility shall establish reasonable
interconnection procedures to facilitate the wheeling of power from
unsuccessful bidders to wholesale purchasers of power.
(7)
Contract negotiations.
(i) Contract negotiations between the utility
and a potential supplier of electricity shall be in strict accordance with the
utility's RFP. Contract negotiations may not be extensive. Fundamental changes
in the nature of the project and purchase payments may not be negotiated. The
fully executed contract shall include provisions that assure a facility's
performance and continued availability under that contract.
(ii) Security provisions for levelized
contracts may not be onerous or anticompetitive.
(iii) Line loss savings are a matter of
location integration with the current system and may be incorporated in final
contracts when negotiated.
(iv) The
price negotiated to be paid to the successful bidder for power shall reflect
its share of necessary upgrades to the transmission system. The utility is
encouraged to establish a standard contribution format for partial compensation
by power producers to transmission system upgrades where these upgrades can be
negotiated.
(v) Promptly upon the
completion of contract negotiations, the utility shall submit a petition to the
Commission seeking approval of the contract and cost recovery.
(8)
Purchases outside of a
bidding program.
(i) A utility with
a competitive bidding program under this subsection may refuse offers of
capacity that are made outside of that bidding program. Energy-only shall be
purchased from an offering qualifying facility under subsection (b).
(ii) When a utility and a potential supplier
of capacity resources intends to negotiate a purchased power contract outside
of the utility's competitive bidding program, the parties shall jointly file a
petition for waiver of this subchapter under §
5.43 (relating to petitions for
issuance, amendment, waiver or repeal of regulations). The parties shall
demonstrate that the transaction cannot be accommodated in the competitive
bidding program and that the purchase is in the public interest from both a
cost and reliability standpoint.
(iii) An electric utility may file a petition
for permission to construct its own generating plant outside of a competitive
bidding program. The Commission will hold hearings on the utility's petition
and the Commission will adopt a final order within 210 days after the petition
is filed. If the Commission does not adopt a final order within that time, the
utility's petition for permission to construct its own generating plant outside
of a competitive bidding process shall be deemed approved as filed, requiring
no further action by the Commission or the utility. The Commission may consider
the following factors in reviewing the electric utility's proposal:
(A) The electric utility's proposal is the
best least-cost option compared to other options.
(B) The electric utility's proposal has the
lowest rate impact compared to other options.
(C) The electric utility's proposal has the
best reliability standard compared to the reliability offered by other
competitors.
(D) The utility's
proposal offers the greatest improvement in the electric utility's financial
standing.
(E) The electric
utility's proposal offers the largest economies of scale and best optimum fuel
mix.
(F) Other factors which the
Commission believes are in the public interest.
(9)
Disputes.
(i) The Commission will determine the dispute
resolution process to be followed during the course of a competitive bidding
program in its final order on the utility's petition filed under paragraph
(3).
(ii) Disputes concerning the
competitive bidding process specific to the unsuccessful bidder shall be
brought to the Commission as a Petition for Reconsideration within 15 days of
the Commission's final order on the utility's petition for contract approval
and cost recovery.
(iii) The
Commission will refer disputes concerning the administrative process of the RFP
to the Office of the Administrative Law Judge.
(10)
Utility reporting
requirements.
(i) A utility
conducting a competitive bid solicitation shall file a written report to the
Commission within 45 days of the completion of its evaluation of bids received.
This report shall describe in detail the evaluation of the bids and the
electric utility's comparison of the bids received to its own construction
options. The report will be treated as proprietary information.
(ii) A second report shall be prepared as a
public document and accompany the proprietary report.
(iii) A utility shall cooperate fully with
Commission staff in review of the solicitation and evaluation
process.
This section cited in 52 Pa. Code §
57.31 (relating to definitions);
52 Pa. Code §
57.32 (relating to purpose and
scope); and 52 Pa. Code §
57.146 (relating to system cost
data).