Pennsylvania Code
Title 52 - PUBLIC UTILITIES
Part I - Public Utility Commission
Subpart C - Fixed Service Utilities
Chapter 57 - ELECTRIC SERVICE
Subchapter B - SERVICE AND FACILITIES
Section 57.24 - Adjustment of bills for average meter error
Current through Register Vol. 54, No. 38, September 21, 2024
(a) Average meter error. In meter tests made by the public utility or by the Commission at the request of a customer, the correctness of adjustment of the meter and its performance in service shall be judged by its average error, determined as follows:
(b) Fast meters. If, upon testing, a meter is found to have an average meter error of more than 2% fast, the public utility shall refund to the customer the overcharge, based upon the corrected meter reading for a period equal to 1/2 the time elapsed since the last previous test, but not to exceed 12 months. If the period of registration error is definitely fixed, the overcharge shall be computed for the period. If the meter has not been tested in accordance with § 57.20 (relating to watthour meter testing), the period for which it has been in service beyond the regular test period shall be added to the 12 months in computing the refund.
(c) Slow meters. If, upon testing, a meter is found to have an average meter error of more than 2% slow, the public utility may render a bill for the service furnished, but not covered by bills previously rendered, for a period equal to 1/2 the time elapsed since the last previous test, but not to exceed 3 months. If the period of registration error is definitely fixed, the charge may be computed for the period.
(d) Access to meters. The public utility shall, at reasonable times, have access to meters, service lines and other property owned by it on premises of customers, for purposes of maintenance and operation. Neglect or refusal on the part of customers to provide reasonable access to their premises for these purposes is deemed to be sufficient cause for the discontinuance of service.
The provisions of this §57.24 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 1501 and 1504.
This section cited in 52 Pa. Code § 57.254 (relating to approval of advanced meters).