Section 43.91 - Loose rock

Universal Citation: 34 PA Code ยง 43.91

Current through Register Vol. 54, No. 38, September 21, 2024

(a) After the blast is fired, loosened pieces of rock shall be scaled from the sides of the excavation and after the blasting is completed, the entire working chamber shall be thoroughly scaled.

(b) The foreman in charge shall inspect the working chamber and have all loose rock or ground removed and the chamber made safe before proceeding with the work.

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.