Pennsylvania Code
Title 34 - LABOR AND INDUSTRY
Part I - Department of Labor and Industry
Chapter 43 - TUNNEL CONSTRUCTION AND COMPRESSED AIR WORK
Subchapter A - TUNNEL CONSTRUCTION AND WORK IN COMPRESSED AIR
TUNNEL CONSTRUCTION
Section 43.40 - Ventilation

Universal Citation: 34 PA Code ยง 43.40
Current through Register Vol. 54, No. 38, September 21, 2024

The constructor of every shaft or tunnel shall provide and maintain a ventilating system with a capacity of at least 75 cubic feet per man per minute or, if horses and mules are used, at least 175 cubic feet per horse or mule per minute. The ventilating system, immediately after blasting has occurred, shall be capable of removing 4,000 cubic feet per minute and entirely removing the contaminated air in 15 minutes.

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.