Section 43.27 - Loose rock

Universal Citation: 34 PA Code ยง 43.27

Current through Register Vol. 54, No. 38, September 21, 2024

(a) The superintendent of the tunnel shall order a competent person to make a daily inspection of the roof. All loose pieces of rock shall be removed from the roof and sides of the excavation.

(b) After a blast is fired, loosened pieces of rock shall be scaled from the roof and sides of the excavation. After the blasting is completed, the entire locality shall be thoroughly scaled and all loose rock or ground shall be removed and the excavation made safe before proceeding with the work.

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.