(a) The following clearances apply for boilers installed after January 1, 1960:
(b) The following requirements apply to a single installation or assembly of storage water heaters or instantaneous water heaters, which operate as a unit:
(c) A new building containing multiple boiler installations must meet the following minimum overhead clearance requirements:
(d) Subsections (a) and (b) do not apply to pressure vessels of factory assembled package units that are governed by § 3a.111 (relating to field inspections) if there is adequate clearance for operation and inspection. Subsection (a) applies to the entire factory assembled unit.
(e) The minimum clearance around a wall-hung boiler must be 30 inches except for the wall mount side.
(f) The clearance between modules in a modular system may be reduced to the manufacturer's recommendations if the entire modular boiler system meets the 30-inch clearance requirement of subsection (a)(1).
(g) This section does not apply to a miniature boiler if the boiler can be safely inspected as installed.
(h) Tripping hazards are not permitted.
This section cited in 34 Pa. Code § 3a.98 (relating to plan approval); 34 Pa. Code § 3a.161 (relating to modular boilers); and 34 Pa. Code § 3a.166 (relating to miniature boilers and kitchen equipment).