Section 963.18 - Project implementation and reporting
Current through Register Vol. 54, No. 44, November 2, 2024
(a) For each project approved by the Board, the administrative staff will develop financial assistance documents which will, among other things, define the terms and conditions under which the financial assistance is offered, the project management plan, project cost breakdown, project scope and other legal documents determined to be necessary by the Authority.
(b) Before beginning construction work, the applicant and its engineer shall confer with the Department project engineer to confirm the scope and schedule of the project and schedule periodic inspections by the Department. The applicant shall begin construction of the project, in accordance with its application, within 12 months of approval by the Board. If the applicant does not begin implementation within 12 months and continue work without unreasonable interruption, the financial assistance may be withdrawn by the Board.
(c) The applicant may not deviate from the scope, approved design or time schedule for a project unless written approval is given by the Authority.
(d) A request for a disbursal of financial assistance shall be on forms approved by the Authority and shall be submitted on a schedule approved by the Authority.
(e) The applicant shall maintain project progress and financial records, to substantiate expenditures and activities shown on the approved Organization and Management Plan and budget for the project.
(f) The applicant shall furnish the Authority with status reports at the Authority's request until the project is completed. The applicant shall also provide the Authority with its annual financial report for each year throughout the repayment period of a loan provided by the Authority.
(g) If the applicant fails to comply with this section, the Authority may withdraw the remaining funds allocated to the project, as well as take other action to which it is legally entitled to take.