(a) Advance funding assistance. The Authority may make funding available to finance those activities undertaken prior to application for construction financing-for example, feasibility analyses, design and engineering work. Definitions, provisions, restrictions, procedures and authorizations that are enumerated in the act and in this chapter apply in the same manner to advance funding assistance as they do to construction financing assistance, except as modified by subsections (b)-(i).
(b) Types of assistance.
(c) Terms of loans. Advance funding loans will be for a term of up to 5 years. Repayment will begin at the completion of the feasibility analysis or design and engineering work-as applicable-funded by this loan. If the recipient of an advance funding loan subsequently receives a higher level of Authority assistance-for example, for either design and engineering or construction, as applicable-the outstanding balance of the advance funding loan may be subsumed in this assistance and, in the case of a subsequent loan, carry the terms established by that subsequent loan.
(d) Funding limitations. Section 963.17 (relating to funding limitations) applies, with the exception that the applicable funding limits shall be 10% of the amounts specified in § 963.17(f). In other cases, the provisions established pursuant to construction are applicable to feasibility analyses or design and engineering, as is appropriate.
(e) Total amount of available advance funding assistance. It will be the Authority's general goal to set aside up to 10% of total available financial assistance for advance funding during a fiscal year. This percentage can be exceeded with an affirmative vote of nine members of the Board.
(f) Additional requirements for applications.
(g) Continuation of overall project. A recipient of financial assistance for advance funding shall initiate construction of the proposed project in accordance with the time frames established by the Authority at the time of approval. If the recipient fails to implement the proposed project in accordance with either the original approved time frame schedule or an amended schedule approved by the Authority, funds disbursed to the recipient by the Authority shall immediately be due and payable. The Authority will exercise power it deems necessary or appropriate under section 6 of the act (35 P. S. § 751.6) to effectuate the repayment of these amounts.
(h) Effect of advance funding assistance. The awarding of advance funding assistance will not have an effect on the priority or ranking of subsequent applications submitted by the recipient for higher levels of Authority assistance.
(i) Limitation. Advance funding assistance will not be made available that might jeopardize or compromise a source of Authority funds.