Pennsylvania Code
Title 25 - ENVIRONMENTAL PROTECTION
Part I - Department of Environmental Protection
Subpart D - Environmental Health and Safety
Article VIII - Municipal Waste
Chapter 283 - RESOURCE RECOVERY AND OTHER PROCESSING FACILITIES
Subchapter B - APPLICATION REQUIREMENTS
GENERAL PROVISIONS
Section 283.106 - Soil erosion and sedimentation control plan

Universal Citation: 25 PA Code ยง 283.106

Current through Register Vol. 54, No. 44, November 2, 2024

(a) The applicant shall submit a plan to manage surface water and control erosion during all phases of construction and operation at the facility. The plan shall be based on the requirements of § 283.232 (relating to soil erosion and sedimentation control), Chapter 102 (relating to erosion and sediment control) and other applicable State and Federal requirements. Calculations indicating water quantities shall be based on the 24-hour precipitation event in inches to be expected once in 25 years.

(b) The plan shall include fully dimensioned diversion ditches, indicating length, gradient and cross section for configuration by reach, and capacities for ditch volume by reach. The calculations which are necessary to support design and siting shall be included in the plan.

This section cited in 25 Pa. Code § 284.310 (relating to application requirements).

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.