Section 289.132 - Operation plan
Current through Register Vol. 54, No. 52, December 28, 2024
An application shall contain a description of the residual waste disposal impoundment operations proposed during the life of the facility within the proposed permit area, including, at a minimum, the following:
(1) A narrative describing the type and method of residual waste disposal impoundment procedures, procedures for inspection and monitoring of incoming waste, sequence of disposal activity, type of disposal activity, proposed engineering techniques and the major equipment to be used under § 289.225 (relating to equipment), using the maps and grids required by § 289.133 (relating to map and grid requirements) as a basis for the description.
(2) A narrative explaining the method and schedule for construction, operation, modification, use, maintenance and removal of the following components of the proposed facility, unless their retention is proposed for postclosure land use:
(3) A construction schedule and sequence of operations, and a site preparation plan and a schedule for disposing of solid waste at the site.
(4) An explanation of how the applicant intends to comply with § 289.224 (relating to measurement and inspection of waste).
(5) A plan for assuring that solid waste received at the facility is consistent with the following:
(6) The proposed operating hours of the proposed facility. The operating hours include those hours related to construction and other activities related to operation of the facility.
This section cited in 25 Pa. Code § 289.131 (relating to basic requirements).