(a) Except as provided in subsection (b), the operator shall provide final cover in the following manner:
(b) The Department may waive the cap and drainage layer requirements of subsection (a)(1) and (2) based on a demonstration that it is not necessary to limit infiltration into the waste. The demonstration shall include the following:
(c) Unless alternative design requirements to meet the performance standards in subsection (a)(1) are approved as part of the permit under § 287.231 (relating to equivalency review procedure), the cap shall meet the design requirements set forth for caps in Appendix A, Table II (relating to minimum liner design standards).
(d) The operator shall place final cover within 1 year after disposal in the final lift ceases or as soon thereafter as weather permits, unless the Department, in the permit, allows a later period based on a demonstration that a later period is necessary to protect the cap and drainage layer from differential settlement of waste at the facility. The Department will not allow a later period unless, at a minimum, delayed installation will not cause or allow violations of this article, the act or the environmental protection acts.
(e) The layer of material described in subsection (a)(3) shall meet the following performance standards. The layer shall:
(f) Unless alternative design requirements to meet the performance standards in subsection (e) are approved as part of the permit under § 287.231 (relating to equivalency review procedure) the layer of material described in subsection (a)(3) shall meet the following design requirements:
(g) The grade of final slopes shall be designed, installed and maintained to accomplish the following:
(h) Unless the Department authorizes a different slope design in the permit based on a demonstration that the different design can meet the requirements of subsection (g), slopes shall be designed, installed and maintained as follows:
This section cited in 25 Pa. Code § 288.141 (relating to compaction and cover plan); and 25 Pa. Code § 288.232 (relating to topsoil storage).