Pennsylvania Code
Title 25 - ENVIRONMENTAL PROTECTION
Part I - Department of Environmental Protection
Subpart D - Environmental Health and Safety
Article IX - Residual Waste Management
Chapter 287 - RESIDUAL WASTE MANAGEMENT-GENERAL PROVISIONS
Subchapter C - GENERAL REQUIREMENTS FOR PERMITS AND PERMIT APPLICATIONS
TRANSITION SYSTEM FOR EXISTING FACILITIES
Section 287.115 - Filing by permitted facilities
Current through Register Vol. 55, No. 13, March 29, 2025
(a) Preliminary application. By July 4, 1994, each operator of a residual waste disposal or processing facility that is authorized by a permit issued by the Department under the act, or, for disposal impoundments, The Clean Streams Law, before July 4, 1992, shall file with the Department a preliminary application for permit modification under this section or a closure plan under § 287.117 (relating to closure plan).
(b) Differences. The preliminary application for permit modification for a residual waste processing or disposal facility shall describe differences between the existing permit and the requirements of this article, including the following areas:
(c) Modification.
(d) Complete application. Within a period not to exceed 9 months after receiving notice from the Department, a person or municipality that filed a preliminary application for permit modification shall file with the Department a complete application for permit modification to correct differences between the existing permit and the requirements of this chapter. The Department's notice may specify a period of less than 9 months.
(e) Deadline for allowing interim operation.. By July 4, 1994, a person or municipality that operates a facility subject to this section may not dispose or process waste at the facility unless a preliminary application for permit modification or a closure plan is filed under this section.
(f) Deadline for allowing continued operation. By July 4, 1997, a person or municipality that operates a facility subject to this section may not store, dispose or process waste at the facility unless one of the following applies:
(g) Closure plan . A person or municipality that is required under subsection (e) or (f) to cease storage, disposal or processing of waste shall submit a closure plan under § 287.117 (relating to closure plan). An application for a new permit shall be filed in accordance with this article to receive, process or dispose of solid waste.
This section cited in 25 Pa. Code § 287.112 (relating to storage impoundments and storage facilities); 25 Pa. Code § 287.116 (relating to interim operational requirements); 25 Pa. Code § 287.117 (relating to closure plan); 25 Pa. Code § 287.118 (relating to Departmental responsibilities); 25 Pa. Code § 287.141 (relating to permit application fee); 25 Pa. Code § 287.221 (relating to permit reissuance); 25 Pa. Code § 287.222 (relating to permit notification); and 25 Pa. Code § 287.312 (relating to existing facilities).