Section 127.443 - Operating permit requirements
Current through Register Vol. 55, No. 13, March 29, 2025
(a) A person may not cause or permit the operation of a source the construction, modification or reactivation of which, or the installation of an air cleaning device on which, is subject to § 127.11 (relating to plan approval requirements), unless the Department has issued a permit to operate the source.
(b) The permit shall be issued with the condition that the source shall operate in compliance with the plan approval, the conditions of the plan approval and the conditions of the operating permit. The Department may issue the permit with additional appropriate conditions.
(c) The Department will not issue an operating permit unless the source was constructed in accordance with the plan approval and the conditions of the plan approval.