Section 109.1105 - Permit requirements
Current through Register Vol. 55, No. 13, March 29, 2025
(a) General permit requirements. A person may not construct, substantially modify or operate corrosion control treatment facilities to comply with this subchapter without having obtained the appropriate permit approvals under Subchapter E (relating to permit requirements) and this section.
(b) Construction permits and permit amendments. The water supplier shall submit an application for a public water system construction permit for a newly-created system or an amended construction permit for a currently-permitted system for corrosion control treatment facilities by the applicable deadline established in § 109.1102(b)(2) (relating to action levels and treatment technique requirements), unless the system complies with paragraph (1) or (2) or otherwise qualifies for a minor permit amendment under § 109.503(b) (relating to public water system construction permits). The permit application must comply with § 109.503 and contain the applicable information specified therein. The application must include recommended water quality parameter performance requirements for optimal corrosion control treatment as specified in § 109.1102(b)(5) and other data, information or documentation necessary to enable the Department to consider the application for a permit for construction of the facilities.
(c) Operation permits. Except for nontransient noncommunity water systems complying with subsection (b)(2), the water supplier shall obtain an operation permit or amended operation permit following completion of construction and prior to initiation of operation of corrosion control treatment facilities. The permit will be issued in accordance with § 109.504 (relating to public water system operation permits). The Department will not issue an operation permit under this subchapter unless the water system complies with the operation and maintenance plan requirements under § 109.1107(b) (relating to system management responsibilities) and the operator certification requirements under § 109.1107(c). The water supplier for a community water system or nontransient noncommunity water system shall submit a request for Department designation of optimal corrosion control treatment performance requirements in accordance with § 109.1102(b)(2) and the Department will issue an amended operation permit designating the performance requirements as specified in § 109.1102(b)(5).
The provisions of this § 109.1105 amended under section 4(a) of the Pennsylvania Safe Drinking Water Act (35 P.S. § 721.4(a)); and section 1920-A(b) of The Administrative Code of 1929 (71 P.S. § 510-20(b)).
This section cited in 25 Pa. Code § 109.1102 (relating to action levels and treatment technique requirements); and 25 Pa. Code § 109.1106 (relating to design standards).