PERMIT ISSUANCE, TRANSFER AND REVOCATION
Section 105.29a - Burden of proof

Universal Citation: 25 PA Code § 105.29a
Current through Register Vol. 55, No. 13, March 29, 2025

In a civil or administrative action taken by the Department under this chapter, the person against whom the action has been taken has the burden of proof to demonstrate that the project complies with the act and this chapter.

The provisions of this § 105.29a issued under the Dam Safety and Encroachments Act (32 P. S. §§ 693.1-693.27); The Clean Streams Law (35 P. S. §§ 691.1-691.1001); section 7 of the act of June 14, 1923 (P. L. 704, No. 294) (32 P. S. § 597); sections 514, 1901-A, 1908-A, 1917-A and 1920-A of The Administrative Code of 1929 (71 P. S. §§ 194, 510-1, 510-8, 510-17 and 510-20); and the Flood Plain Management Act (32 P. S. §§ 679.101-679.601).

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.