Section 88.507 - Treatment of discharges
Current through Register Vol. 55, No. 13, March 29, 2025
(a) Except for pre-existing discharges which are not encountered during mining or the implementation of the pollution abatement plan, the operator shall comply with §§ 88.92, 88.187 and 88.292 (relating to hydrologic balance: effluent standards).
(b) Except as provided in § 88.510(d) (relating to effluent limitations), the operator shall treat the pre-existing discharges which are not encountered during mining or implementation of the pollution abatement plan to comply with the effluent limitations established by best professional judgment. The effluent limitations established by best professional judgment may not be less than the baseline pollution load. If the baseline pollution load when expressed as a concentration for a specific parameter satisfies the effluent limitations at §§ 88.92, 88.187 and 88.292 for that parameter, the operator shall treat the pre-existing discharge for that parameter to comply with effluent limitations established by best professional judgment or the effluent limitations at §§ 88.92, 88.187 and 88.292.
(c) For purposes of subsections (a) and (b), the term "encountered" may not be construed to mean diversions of surface water and shallow groundwater flow from areas undisturbed by the implementation of the pollution abatement plan which would otherwise drain into the affected area, so long as the diversions are designed, operated and maintained under §§ 88.95(b)-(g), 88.190(b)-(g) and 88.295(b)-(i) (relating to hydrologic balance: diversions; hydrologic balance: diversions; and hydrologic balance: diversions and conveyances).
(d) An operator required to treat pre-existing discharges will be allowed to discontinue treating the discharges under this section when the operator affirmatively demonstrates to the Department's satisfaction that:
(e) If after discontinuance of treatment of discharges under subsection (d) the discharges fail to meet the effluent limitations established by subsection (b), the operator shall reinstitute treatment of the discharges in accordance with subsection (b). An operator who reinstitutes treatment under this subsection will be allowed to discontinue treatment if the requirements of subsection (d) are met.
(f) Discontinuance of treatment under subsection (d) may not be deemed or construed to be or to authorize a release of bond under § 88.509 (relating to criteria and schedule for release of bonds on pollution abatement areas).
(g) If four consecutive weekly determinations of pollution load, as required under § 88.506(3)(i) (relating to operational requirements), exceed one or more triggers, the permittee shall notify the Department and begin treatment within 30 days of the fourth sample in accordance with the treatment limits established in the permit.
(h) If the Department determines, through analysis of any data submitted pursuant to the monitoring requirements or any data collected by the Department, that there has been pollution loading degradation at any of the monitoring points or hydrologic units, the Department will notify the permittee accordingly. The permittee shall begin treatment within 30 days in accordance with the treatment limits established in the permit.
(i) Any pre-existing pollutional discharge which is an encountered discharge shall be treated to the effluent limitations in the permit until the discharge is no longer encountered.
(j) For the purposes of determining applicable effluent limitations, a discharge will continue to be deemed to be an encountered discharge until the surface mining area which has been disturbed and which contributes to the discharge has been backfilled and regraded, and revegetation work has started.
The provisions of this § 88.507 amended under section 5 of The Clean Streams Law (35 P.S. § 691.5); sections 4(a) and 4.2 of the Surface Mining Conservation and Reclamation Act (52 P.S. §§ 1396.4(a) and 1396.4b); section 1920-A of The Administrative Code of 1929 (71 P.S. § 510-20); section 3.2 of the Coal Refuse Disposal Control Act (52 P.S. § 30.53b); and section 7(b) of The Bituminous Mine Subsidence and Land Conservation Act (52 P.S. § 1406.7(b)).
This section cited in 25 Pa. Code § 86.159 (relating to self-bonding); and 25 Pa. Code § 88.509 (relating to criteria and schedule for release of bonds on pollution abatement areas).