Section 88.199 - Hydrologic balance: permanent postmining renovation of sedimentation ponds, diversions, impoundments and treatment facilities

Universal Citation: 25 PA Code § 88.199
Current through Register Vol. 55, No. 13, March 29, 2025

At the completion of bank removal and reclamation activities, the person who conducts the bank removal and reclamation activities shall renovate all permanent sedimentation ponds, diversions, impoundments and treatment facilities to meet criteria specified in the detailed design plan for the permanent structures and impoundments.

Disclaimer: These regulations may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.