(a) Available soil, as required by § 88.86 (relating to vegetation-supporting material: general requirements), shall be removed from the area to be disturbed prior to any surface mining.
(b) In the event that removal of vegetative matter, soil or other materials may result in erosion which may cause air or water pollution, the size of the area from which soil is removed at any one time shall be limited and other measures shall be taken that the Department may approve or require to control erosion.
(c) If the soil is less than 12 inches in depth, all soil and sufficient unconsolidated material immediately below the soil shall be removed to provide a 12-inch layer when redistributed as the final surface.
(d) On areas that have been previously affected by mining with no available soil, the spoil material best suited to support vegetation shall be conserved for redistribution as the final surface.