Section 918-309-0025 - Phased Permitting

Universal Citation: OR Admin Rules 918-309-0025

Current through Register Vol. 63, No. 3, March 1, 2024

(1) During the plan review process, an electrical contractor may request a complete or partial permit before the entire plans and specifications are submitted or approved, if adequate information is provided showing compliance with pertinent portions of the code. The permittee proceeds at his or her own risk, without assurance that the permit for the entire installation will be granted, or that corrections will not be required, including those portions permitted. The partial permit shall allow the electrical contractor to proceed with work pertaining to the electrical system of the structure.

(2) Any inspections performed by the local jurisdiction on the site or of the ground work shall be counted toward the number of electrical inspections allowed by the full permit once plan review is complete and the permit is issued.

Stat. Auth.: ORS 479.730

Stats. Implemented: ORS 479.730

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.