Oregon Administrative Rules
Chapter 918 - DEPARTMENT OF CONSUMER AND BUSINESS SERVICES, BUILDING CODES DIVISION
Division 225 - BOILERS AND PRESSURE VESSELS
Section 918-225-0609 - Use of Minor Repair Permits
Current through Register Vol. 63, No. 12, December 1, 2024
(1) Only those minor repairs described in OAR 918-225-0612 may be performed under a minor repair permit.
(2) A minor repair permit authorizes work on a single boiler or pressure vessel. Multiple minor repairs may be performed under a minor repair permit provided that each minor repair is completed within the five day period that begins when the first minor repair is completed.
(3) All work performed under a minor repair permit must conform to the Oregon Boiler and Pressure Vessel Specialty Code.
(4) An individual performing work under a minor repair permit must:
(5) Within five business days of work being completed, the purchaser of the minor repair permit is responsible for ensuring that all work that was performed under the minor repair permit is recorded in the manner approved by the division.
Publications referenced are available from the agency.
Stat. Auth.: ORS 480.595, 455.154 & 455.155
Stats. Implemented: ORS 480.595, 455.154 & 455.155