Oregon Administrative Rules
Chapter 918 - DEPARTMENT OF CONSUMER AND BUSINESS SERVICES, BUILDING CODES DIVISION
Division 225 - BOILERS AND PRESSURE VESSELS
Section 918-225-0600 - Permits
Current through Register Vol. 63, No. 12, December 1, 2024
(1) Except as otherwise provided in this rule, an installation permit is required before installing, altering, or repairing a nonexempt boiler or pressure vessel.
(2) Notwithstanding section (1) of this rule:
(3) An operating permit or a temporary operation authorization is required before placing a nonexempt vessel into operation.
(4) If an inspection is scheduled, and the inspector is at the site but the boiler or pressure vessel is not ready or cannot be accessed, the rescheduled inspection will be at an additional cost. The fee for such inspections is the hourly rate specified in ORS 480.605.
(5) Permits to operate boilers or pressure vessels shall be issued periodically according to vessel type, based on the schedule established by the division in Table 4-B.
(6) Operating and installation permit fees are as shown in OAR 918-225-0620 Table 3-B.
(7)
(8) Where an installation permit is required, the equipment owner or, if the work will be performed by a contractor, the contractor, must acquire the installation permit prior to beginning the intended installation, repair, or alteration, and notify the deputy or special inspector who will inspect the work. Work may not begin until the inspector has reviewed and approved the work to be performed.
(9) An installation permit or operating permit issued under this rule is not transferable.
(10) An installation permit automatically expires 18 months from the date of issuance unless the installation, alteration, or repair begins before the end of the 18th month.
(11) Any person who commences any work on a boiler or pressure vessel before obtaining the necessary permits shall be subject to an investigative fee. The amount of the investigative fee shall be the average or actual additional cost of ensuring that a boiler or pressure vessel is in conformance with the Oregon Boiler and Pressure Vessel Specialty Code and shall be in addition to the required permit fees.
Publications: Publications referenced are available from the agancy. NOTE: Table referenced is not included in rule text. To view tables referenced in rule text, click here to view rule.
Statutory/Other Authority: 480.595, 480.605 & ORS 480.585
Statutes/Other Implemented: ORS 455.058, 480.585, 480.595, 480.605 & 480.630