Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 95 - RESOURCE ADEQUACY
Section 860-095-0030 - Electricity Service Supplier Resource Adequacy Informational Filing Requirements

Universal Citation: OR Admin Rules 860-095-0030

Current through Register Vol. 63, No. 9, September 1, 2024

(1) Electricity Service Suppliers must submit an Informational Filing with the Commission every other year.

(a) The Informational Filing may be filed as a part of the Emissions Planning Report filing.

(b) The Informational Filing must contain a discussion about how the overall resource strategy interacts with Resource Adequacy concerns.

(2) The Informational Filing for an Electricity Service Supplier must include:

(a) A monthly P50 Peak Load Forecast and Effective Load Carrying Capability curve over a period of the greater of four years or the longest available timeline from a Qualified Regional Program using methods consistent with outputs of the Qualified Regional Program's Advisory Forecast.

(b) A discussion covering at least four years of the transmission rights necessary to serve P50 load, the transmission rights currently owned or used, the steps that will be taken to procure transmission rights to fill in any open position, and any expected constraints or difficulties in filling any open positions.

(3) All publicly available outputs of a Qualified Regional Program's most recent Advisory Forecast must be included with the Informational Filing. These may be included as an appendix chapter.

(4) Availability of Information:

(a) A Regional Participant's most recent Regional Forward Shwoing submission to its Qualified Regional Program must be made available for review only to Qualified Parties and only upon request pursuant to a Modified Protective Order.

(b) The following information shall be available for review only by Non-market Participants that have executed a Modified Protective Order:
(A) A discussion about how the overall resource strategy interacts with Resource Adequacy concerns, as requirebed by section (1)(b)of this rule;

(B) A monthly P50 Peak Load Forecast and Effective Load Carrying Capability curve, as required by section (2)(a) of this rule; and

(C) A discussion covering at least four years of the transmission rights necessary to serve P50 load, the transmission rights currently owned or used, the steps that will be taken to procure transmission rights to fill in any open position, and any expected constraints or difficulties in filling any open positions, as required by section (2)(b) of this rule.

(c) For purposes of this rule, Non-market Participants includes Commission Staff, the Oregon Citizens' Utility Board, and nonprofit organizations engaged in environmental advocacy that do not otherwise participate in electricity markets.

(5) As part of the forecast of monthly P50 Peak Load Forecast and monthly forecast of transmission requirements, an Electricity Service Supplier must use current load levels or provide reasonable substitutes of the load forecast. An Electricity Service Supplier is responsible for demonstrating that the substitute load forecast is reasonable.

Statutory/Other Authority: ORS 183 & ORS 756

Statutes/Other Implemented: ORS 756.040, ORS 757.649 & ORS 757.659

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.