Section 860-095-0020 - Electric Company Resource Adequacy Informational Filing Requirements
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Electric Companies must provide an Informational Filing to the Commission as a part of their Integrated Resource Plan. The Electric Company's Informational Filing must be included as a chapter to the Integrated Resource Plan that incorporates the Advisory Forecast from a Qualified Regional Program and contains a discussion about how the overall resource strategy interacts with Resource Adequacy concerns.
(2) The Informational Filing for an Electric Company must include:
(3) All outputs of a Qualified Regional Program's most recent Advisory Forecast must be included with the Informational Filing. These may be included in the Informational Filing or as an Appendix chapter to the Integrated Resource Plan.
(4) A Regional Participant's most recent Regional Forward Showing submission to its Qualified Regional Program must be made available to Qualified Parties upon request pursuant to a Modified Protected Order.
Statutory/Other Authority: ORS 183 & ORS 756
Statutes/Other Implemented: ORS 756.040, ORS 756.700, ORS 756.105 & ORS 757.659