(1) No later than July 1, 2029, and no later than July 1 for each year thereafter, the electric company must file a report with the Commission demonstrating compliance or explaining in detail any failure to comply, with the standard in ORS 469A.210(2).
(2) The report required in section (1) of this rule must include the following information associated with each owned or contracted eligible renewable energy project:
(3) The report required in section (1) of this rule must include the following information regarding the electric company's aggregate electrical capacity that serves Oregon load during the reporting year:
Statutory/Other Authority: ORS 756.060, ORS 469A.200 & ORS 469A.210