Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 88 - COMMUNITY SOLAR PROGRAM RULES
Section 860-088-0100 - Consumer Protection Provisions
Current through Register Vol. 63, No. 9, September 1, 2024
(1) All contracts between Project Managers and participants must contain provisions to protect customers, including terms and conditions regarding:
(2) Prior to executing a contract with a participant, the Project Manager must provide the participant a Commission-approved checklist that discloses the charges, terms and conditions of service, the process for dispute resolution, and other items set forth in the Program Implementation Manual.
(3) Marketing materials must contain a Commission-approved disclaimer explaining that participation in the Community Solar Program is for the purpose of offsetting participants' energy usage with electricity generated by certified projects.
Stat. Auth.: OL 2016, ch. 28, sec. 22
Stats. Implemented: OL 2016, ch. 28, sec. 22