Section 860-088-0050 - Project Certification
Universal Citation: OR Admin Rules 860-088-0050
Current through Register Vol. 63, No. 9, September 1, 2024
(1) The Project Manager of a pre-certified project must submit an application for project certification to the Program Administrator.
(2) The Commission will certify a project that demonstrates:
(a) Ownership of, or
subscription to, at least 50 percent of the project nameplate capacity;
(b) Ownership or subscription by
at least five different participants;
(c) Compliance with applicable low-income
capacity requirements;
(d)
Commission approval of modification to pre-certified project as required in OAR
860 088-0040(6), if applicable; and
(e) Satisfaction of any other condition
identified by the Commission at the time of pre certification.
(3) The Program Administrator reviews applications for certification in the order received for compliance with applicable requirements and presents applications to the Commission for certification. The Program Administrator must notify the Project Manager of any deficiencies and allow reasonable time for remedy.
Stat. Auth.: OL 2016, ch. 28, sec. 22
Stats. Implemented: OL 2016, ch. 28, sec. 22
Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.