Section 860-084-0400 - Data Collection
Current through Register Vol. 63, No. 9, September 1, 2024
Except as provided in OAR 860-084-0440, each electric company must collect from the retail electricity consumer participating in the pilot program data on the installed solar photovoltaic system. The collected data elements must include, but are not limited to:
(1) Nameplate Capacity;
(2) Total Installed Cost;
(3) Photovoltaic module cost;
(4) Non-photovoltaic module cost (including inverters, other hardware, labor, overhead, and regulatory compliance costs);
(5) Total financing cost;
(6) Financing terms (including fees paid, loan term, and interest rate secured);
(7) System location, including street address and GPS location;
(8) Technology type (building-integrated versus rack-mounted, crystalline silicon versus thin-film, solar tracking versus rack-mounted, etc.);
(9) Federal tax credit;
(10) In-service date;
(11) Expected annual energy output;
(12) Date of certification of compliance; and
(13) Class of service of retail electricity consumer.
(14) Electric companies must collect data on the time to interconnection agreement and conduct pilot program satisfaction surveys in order to improve capacity reservation and interconnection processes over the pilot program. Data collection and surveys must include:
Stat Auth: ORS 757.360 - 757.380
Stats. Implemented: ORS 757.360 - 757.380