(1) An electric company may recover in rates all costs prudently incurred to offer the pilot program established under these rules, including, but not limited to, costs not otherwise reflected in rates for electricity usage related to:

(a) Payments for the output of contracted systems, and

(b) Data collection and analysis for assessment of the company's pilot program.

(2) On November 1 of 2010, 2012, and 2014, and as otherwise directed by the Commission, each electric company must file for review, in a Commission proceeding, its estimates of the rate impact of pilot program participation, for each customer class, along with supporting work papers.

(3) The Commission may establish total generator nameplate capacity limits for an electric company so that the rate impact of the pilot program for any customer class does not exceed 0.25 percent of the company's revenue requirement for the class in any year.

Stat Auth: ORS 757.360 - 757.380

Stats. Implemented: ORS 757.360 - 757.380

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.