Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 82 - SMALL GENERATOR INTERCONNECTION RULES
Section 860-082-0045 - Tier 1 Interconnection Review
Current through Register Vol. 63, No. 9, September 1, 2024
(1) A public utility must use the Tier 1 review procedures when an applicant submits an application to interconnect a small generator facility that meets the following requirements:
(2) Tier 1 Approval Criteria. A public utility must approve an application for interconnection under the Tier 1 interconnection review procedures if the small generator facility meets the approval criteria in subsections (a) through (f). A public utility may not impose different or additional approval criteria.
(3) In addition to the timelines and requirements in OAR 860-082-0025, the public utility must provide written notice to the applicant stating whether the small generator facility meets the Tier 1 approval criteria no later than 15 business days from the date a Tier 1 interconnection application is deemed complete. If a public utility does not notify an applicant whether the interconnection is approved or denied within 20 business days after the application is deemed complete, the interconnection will be deemed approved.
(4) Interconnection after passing screens. If the proposed interconnection passes the screens, the public utility must follow the requirements in OAR 860-082-0025(7)(f).
(5) Approval despite screen failure. Despite the failure of one or more screens, the public utility, at its sole option, may approve the interconnection provided such approval is consistent with safety and reliability. If the public utility determines that the small generator facility can be interconnected safely if minor modifications to the transmission or distribution system were made (for example, changing meters, fuses, or relay settings), then the public utility must offer the applicant a good-faith, non-binding estimate of the costs of such proposed minor modifications. Modifications are not considered minor under this section if the total cost of the modifications exceeds $10,000. If the applicant authorizes the public utility to proceed with the minor modifications and agrees to pay the entire cost of the modifications, then the public utility must approve the application.
(6) Process after screen failure. If the public utility cannot determine that the small generator facility may nevertheless be interconnected consistent with safety, reliability, and power quality standards, at the time the public utility notifies the applicant of the Tier 1 review results, the public utility must provide the applicant with:
(7) Applicant options meeting. If the applicant requests an applicant options meeting, the public utility shall offer to convene a meeting at a mutually agreeable time within 15 business days of the applicant's request. At the applicant options meeting the public utility shall provide the applicant the opportunity to review the screen analysis and related results, to designate a different RPA, to review possible customers-generator modifications, and to discuss what further steps are needed to permit the small generator facility to connect safely and reliably.
(8) The interconnection process is not complete until:
Statutory/Other Authority: ORS 183, ORS 756 & ORS 757
Statutes/Other Implemented: ORS 756.040 & ORS 756.060