Current through Register Vol. 63, No. 12, December 1, 2024
(1) A
person may not interconnect a small generator facility to a public utility's
transmission or distribution system without authorization from the public
utility.
(a) A person proposing to
interconnect a new small generator facility to a public utility's transmission
or distribution system must submit an application to the public
utility.
(b) A person with an
existing interconnected small generator facility who proposes to make any
change to the facility, other than a minor equipment modification, must submit
an application to the public utility. This includes changes affecting the
nameplate rating of the existing interconnected small generator facility or the
output capacity authorized in the agreement governing the terms of the
interconnection.
(c) An applicant
with a pending completed application to interconnect a small generator facility
must submit a new application if the applicant proposes to make any change to
the small generator facility other than a minor equipment modification. This
includes changes affecting the nameplate rating of the proposed small generator
facility.
(A) The applicant relinquishes the
queue position assigned to the pending completed application, and the public
utility assigns a new queue position based on the date and time the public
utility receives the new application.
(B) If the new application is submitted
within 30 business days of the date of submission of the original application,
then the public utility must apply the original application fee to the
application fee required for the new application.
(d) A person with a pending completed
application to interconnect a net metering facility or a FERC jurisdictional
generator who proposes to change the facility to a small generator facility
must submit a new application under the small generator interconnection rules.
(A) The applicant relinquishes the queue
position assigned to the pending completed application, and the public utility
assigns a new queue position based on the date and time that the
interconnecting public utility receives the small generator interconnection
application.
(B) If the small
generator interconnection application is received within 30 business days of
the date of submission of the original net metering or FERC jurisdictional
generator interconnection application, then the public utility must apply the
original application fee to the application fee required for the new
application.
(e) An
interconnection customer must submit an application to renew an existing small
generator facility interconnection before the expiration of the interconnection
agreement between the interconnection customer and the interconnected public
utility. The application must be submitted no later than 60 business days
before the interconnection agreement's expiration date.
(A) A public utility may not unreasonably
refuse to grant expedited review of an application to renew an existing small
generator facility interconnection if there have been no changes to the small
generator facility other than minor equipment modifications.
(B) A public utility may not require an
existing small generator facility to undergo Tier 4 review if there have been
no changes to the small generator facility other than minor equipment
modifications and there have been no material changes to the portion of the
public utility's transmission or distribution system affected by the
interconnection of the small generator facility.
(C) A public utility may require the
interconnection customer to pay for interconnection facilities, system
upgrades, or changes to the small generator facility or its associated
interconnection equipment that are necessary to bring the small generator
facility interconnection into compliance with the small generator
interconnection rules or IEEE 1547 or 1547.1.
(D) If the public utility has not completed
its review of an application to renew and a new interconnection agreement is
not signed before the expiration of the current interconnection agreement
governing the interconnection of an existing small generator facility to a
public utility's transmission or distribution system, then the current
interconnection agreement remains in effect until the renewal process is
completed and a new interconnection agreement is signed.
(2) All applications must be made
using the appropriate application form and must follow the standard form
applications developed by the public utility and approved by the Commission.
The public utility must provide separate application forms for review under
Tier 1 and for review under Tiers 2, 3, and 4. The Tier 1 application form must
include an unexecuted interconnection agreement. The public utility must
provide a copy of an application form to any person upon request and must post
copies of the application forms on the public utility's website.
(a) Applicants must use the Tier 1
application form for a small generator facility that meets the requirements of
OAR 860-082-0045(1).
(b) All
applicants may use the application form for Tiers 2, 3, or 4.
(3) A public utility may require
payment of a nonrefundable application processing fee. The amount of the fee
depends upon the review tier requested in the application and is intended to
cover the reasonable costs of processing and evaluating the application.
(a) The application fee may not exceed $100
for Tier 1 review, $500 for Tier 2 review, and $1,000 for review under Tiers 3
and 4.
(b) An applicant must pay
the reasonable costs incurred by the public utility to perform any studies and
engineering evaluations permitted by these rules and necessary to evaluate the
proposed application to interconnect. Before the public utility may assess any
costs in excess of the application fee, the public utility must receive written
authorization from the applicant. If the applicant does not authorize the
additional costs, then the application is deemed withdrawn, and the original
application fee is forfeited.
(c)
If an application is denied at one review tier, and the applicant resubmits the
application at a higher review tier within 15 business days after the date the
applicant received notification of the denial, then the applicant maintains the
queue position assigned to the original application and the public utility must
apply the original application fee and any other fees paid in conjunction with
the original application to the fees applicable to the resubmitted
application.
(4) If an
applicant proposes to interconnect multiple small generator facilities to the
public utility's transmission or distribution system at a single point of
interconnection, then the public utility must evaluate the applications based
on the combined total nameplate rating for all of the small generator
facilities. If the combined total nameplate rating exceeds 10 megawatts, then
the small generator interconnection rules do not apply.
(5) An applicant must provide documentation
of site control with an interconnection application. Site control may be
demonstrated through ownership of the site, a leasehold interest in the site,
or an option or other right to develop the site for the purpose of constructing
the small generator facility. Site control may be documented by a property tax
bill, deed, lease agreement, or other legally binding contract.
(6) A public utility may propose to
interconnect multiple small generator facilities at a single point of
interconnection to minimize costs, and an affected applicant or interconnection
customer may not unreasonably refuse such a proposal. An applicant or
interconnection customer may, however, elect to maintain a separate point of
interconnection if the applicant or interconnection customer agrees to pay the
entire cost of the separate interconnection facilities.
(7) Application review process.
(a) Within 10 business days of receipt of an
application to interconnect a small generator facility, the interconnecting
public utility must provide written notice to the applicant stating whether the
application is complete.
(A) If the
application is incomplete, then the public utility must provide the applicant
with a detailed list of the information needed to complete the application. An
application is deemed complete when the public utility receives the listed
information. The applicant must provide the listed information within 10
business days of receipt of the list, or the application is deemed
withdrawn.
(B) If a public utility
does not have a record of receipt of an application or cannot locate an
application, then the applicant must provide an additional copy of the
application to the public utility. If the applicant can demonstrate that a
complete application was originally delivered to the public utility at a
particular time on a particular date, then the public utility must assign a
queue position to the application based on the original time and date of
delivery.
(b) Once the
public utility deems an application to be complete, the public utility must
assign the application a queue position. An applicant must meet all applicable
deadlines in the small generator interconnection rules to maintain its queue
position unless the deadlines have been waived by agreement with the
interconnecting public utility or by Commission order.
(c) If the public utility determines during
the evaluation process that supplemental or clarifying information is required,
then the public utility must request the information from the applicant, and
the applicant must provide the requested information within 15 business days of
the request, or the application will be deemed withdrawn. The time necessary to
complete the evaluation of the application may be extended by the time required
for the receipt of the additional information. Requests for information do not
affect the applicant's queue position.
(d) A public utility must use IEEE 1547 and
IEEE 1547.1 to evaluate small generator interconnection applications unless
otherwise specified in these rules or unless the Commission grants a waiver to
use different or additional standards.
(e) Reference Point of Applicability Review.
(A) For Tier 4 applications, the public
utility will raise any concerns about the RPA in the scoping meeting.
(B) For Tier 1 through Tier 3 applications,
the public utility notifies an applicant if the proposed RPA is appropriate
when it provides screen results. If the RPA is inappropriate the public utility
will notify the applicant in writing, including an explanation as to why it
requires correction. The applicant must resubmit the application with the
corrected RPA within ten business days. If the applicant does not provide the
appropriate RPA, a request for an extension of time, or request an applicant
options meeting within the deadline, the application will be deemed
withdrawn.
(f)
Interconnection Agreement. If the proposed interconnection is approved and
requires no construction of facilities by the public utility, the public
utility must provide the applicant an executed interconnection agreement no
later than five business days after approving the interconnection. If the
proposed interconnection is approved and requires construction of facilities,
the public utility must provide the applicant an executed interconnection
agreement, along with a non-binding good faith cost estimate and construction
schedule for any required upgrades, no later than 15 business days after
approving the interconnection. If the applicant does not return a countersigned
interconnection agreement and any required deposit not to exceed the amount in
OAR 860-082-0035(5)(a) to the public utility, or request negotiation of a
non-standard interconnection agreement, within 15 business days of receipt of
an executed interconnection agreement, the application is deemed withdrawn.
(A) An applicant or a public utility is
entitled to the terms in the standard form agreement but may choose to
negotiate for different terms.
(B)
If negotiated changes to a standard interconnection agreement are materially
inconsistent with the small generator interconnection rules, then the applicant
and the public utility must seek Commission approval of the negotiated
interconnection agreement.
(g) The applicant must provide the public
utility written notice at least 20 business days before the planned
commissioning for the small generator facility.
(A) The public utility has the option of
conducting a witness test at a mutually agreeable time within 10 business days
of receipt of the certificate of completion.
(B) The public utility must provide written
notice to the applicant indicating whether the public utility plans to conduct
a witness test or will waive the witness test within three business days of
receipt of the certificate of completion.
(C) If the public utility notifies the
applicant that it plans to conduct a witness test but fails to conduct the
witness test within 10 business days of receipt of the certificate of
completion or within a time otherwise agreed upon by the applicant and the
public utility, then the witness test is deemed waived.
(D) If the witness test is conducted and is
successful, or if the public utility waives the witness test, the public
utility must provide the countersigned certificate of completion within five
business days of conducting the witness test or waiver of witness
test.
(E) If the witness test is
conducted and is not acceptable to the public utility, then the public utility
must provide written notice to the applicant describing the deficiencies within
five business days of conducting the witness test. The public utility must give
the applicant 20 business days from the date of the applicant's receipt of the
notice to resolve the deficiencies. If the applicant fails to resolve the
deficiencies to the reasonable satisfaction of the public utility within 20
business days or at a mutually agreeable time, then the application is deemed
withdrawn.
(h) A public
utility must meet all applicable deadlines in the small generator
interconnection rules unless the deadlines have been waived by agreement with
an applicant or interconnection customer or by Commission order. If the public
utility cannot meet an applicable deadline, then the public utility must
provide written notice to the applicant or interconnection customer explaining
the reasons for the failure to meet the deadline and an estimated alternative
deadline. A public utility's failure to meet an applicable deadline does not
affect an applicant's queue position.