(1) A public utility may not require an applicant whose facility meets the criteria for interconnection approval under the Tier 1 or Tier 2 interconnection review procedure to perform or pay for additional tests, except if agreed to by the applicant.
(2) A public utility may not charge any fee or other charge for connecting to the public utility's distribution system or for operation of a net metering facility for the purposes of net metering, except for the fees provided for under these net metering rules.
(3) Once a net metering interconnection has been approved under these net metering rules, the public utility may not require a customer-generator to test or perform maintenance on its facility except for the following:
(4) When an approved net metering facility undergoes maintenance or testing in accordance with the requirements of these net metering rules, the customer-generator must retain written records for seven years documenting the maintenance and the results of testing.
(5) A public utility has the right to inspect a customer-generator's facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to the customer-generator. If the public utility discovers that the net metering facility is not in compliance with the requirements of these net metering rules, the public utility may require the customer-generator to disconnect the net metering facility until compliance is achieved.
Statutory/Other Authority: ORS 183, ORS 756 & ORS 757
Statutes/Other Implemented: ORS 756.040 & ORS 757.300