Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 36 - WATER UTILITIES
Section 860-036-2390 - Accounting for Construction Work in Progress (CWIP)

Universal Citation: OR Admin Rules 860-036-2390

Current through Register Vol. 63, No. 12, December 1, 2024

(1) This rule applies to rate-regulated water utilities.

(2) CWIP is an accounting treatment for capital improvement projects under construction, but not yet placed in service. The treatment allows rate-regulated water utilities to place recoverable capital improvements costs into plant. The Commission may approve the cost of a specific capital improvement project into rates if:

(a) The capital improvement project is under construction;

(b) The water utility uses the additional revenues solely for the purpose of completing the capital improvement project;

(c) The water utility demonstrates that it is in the public interest to provide funding for the capital improvement through rates; and

(d) The costs are approved by the Commission.

Stat. Auth.: ORS 183, 756, 757

Stats. Implemented: ORS 756.040, 757.120, 757.355

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.