Division 29 - REGULATIONS RELATED TO AGREEMENTS BETWEEN ELECTRIC UTILITIES AND ELECTRIC COGENERATION AND SMALL POWER PRODUCTION FACILITIES
Section 860-029-0080 - Electric Utility System Cost Data
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Each public utility must provide sufficient data concerning its avoided costs and costs of interconnection to allow the owner or operator of a qualifying facility to estimate, with reasonable accuracy, the payment it could receive from the utility if the qualifying facility went into operation under any of the purchase agreements provided for in these rules.
(2) By January 1 of each odd-numbered year, each nonregulated utility must prepare and file with the Commission a schedule of avoided costs equaling the nonregulated utility's forecasted incremental cost of resources over at least the next 20 years.
(3) Each public utility must file with the Commission draft avoided-cost information at the time it files its integrated resource plan and file final avoided-cost information within 30 days of a Commission decision of acknowledgement of the integrated resource plan to be effective 30 days after filing. The information submitted will be maintained for public inspection and include the following data for calculating avoided costs:
(4) Each public utility contracting to purchase nonfirm energy from a qualifying facility under OAR 860-029-0040(3)(a) must file with the Commission each quarter its nonfirm energy avoided cost.
(5) Nothing in these rules shall preclude the determination of avoided costs:
(6) State review: Any data submitted by a public utility under this rule shall be subject to review and approval by the Commission. In any such review, the public utility has the burden of supporting and justifying its data.
(7)
(8) A public utility may propose or the Commission may require a public utility to file the data described in OAR 860-029-0080(3) anytime during the two-year period between filing integrated resource plans to reflect significant changes in circumstances, including, but not limited to, the acquisition of a major block of resources or the completion of a competitive bid. Such a revision will become effective 90 days after filing.
(9) At least every two years, the public utility must file with the Commission the data described in OAR 860-029-0040(4) and 860-029-0080(3).
Statutory/Other Authority: ORS 183, 756, 757, 758
Statutes/Other Implemented: ORS 756.040, 758.505 - 758.555