Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 29 - REGULATIONS RELATED TO AGREEMENTS BETWEEN ELECTRIC UTILITIES AND ELECTRIC COGENERATION AND SMALL POWER PRODUCTION FACILITIES
Section 860-029-0047 - Integration Charges

Universal Citation: OR Admin Rules 860-029-0047

Current through Register Vol. 63, No. 9, September 1, 2024

(1) Each public utility may assess Commission-approved integration charges on wind and solar qualifying facilities that are located within the public utility's Balancing Authority Area.

(2) The public utility bears the burden to establish the proposed integration charge or charges reflecting the costs of integrating the type of resource that will be subject to the charges.

(3) To the extent they are to be imposed by the public utility, any integration charges must be included in the public utility's avoided cost schedules.

Statutory/Other Authority: ORS 183, ORS 756, ORS 757 & ORS 758

Statutes/Other Implemented: ORS 756.040 & ORS 758.505-758.555

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.