Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 29 - REGULATIONS RELATED TO AGREEMENTS BETWEEN ELECTRIC UTILITIES AND ELECTRIC COGENERATION AND SMALL POWER PRODUCTION FACILITIES
Section 860-029-0043 - Standard Rates for Purchase

Universal Citation: OR Admin Rules 860-029-0043

Current through Register Vol. 63, No. 9, September 1, 2024

(1) Each public utility must offer standard non-renewable avoided cost rates to eligible qualifying facilities.

(2) Each public utility that acts to comply with Oregon's renewable portfolio standard must offer standard renewable avoided cost rates to eligible qualifying facilities.

(3) Unless the Commission adopts a higher threshold, all qualifying facilities with a nameplate capacity of 100 kW and less are eligible for standard avoided cost rates.

(4) Each public utility must file standard avoided cost rates that differentiate between qualifying facilities of different resource types by taking into account the contributions to meeting the utility's peak capacity of the different resource types.

(5) Each public utility must update its standard avoided costs in accordance with OAR 860-029-0085.

Statutory/Other Authority: ORS 183, 756, 757, 758

Statutes/Other Implemented: ORS 756.040, 758.505-758.555

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.