(1) A plan of correction must, at a minimum, set out:
(2) If a pole occupant suggests a compliance date of more than 180 days following receipt of a notice of violation, then the pole occupant must show good cause.
(3) Upon its receipt of a plan of correction that a pole occupant submits under OAR 860-028-0150(3)(a), a pole owner must give notice of its acceptance or rejection of the plan.
(4) Pole occupants submitting a plan of correction must report to the pole owner all corrections completed within the timelines provided for within the plan.