Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 25 - REGULATIONS TO PREVENT DUPLICATION OF FACILITIES
Section 860-025-0035 - CPCN Review Criteria
Current through Register Vol. 63, No. 9, September 1, 2024
(1) The Commission may approve a petition filed under OAR 860-025-0030 by determining the necessity, safety, practicability and justification in the public interest of the proposed transmission line upon consideration of the following:
(2) In evaluating a petition under this rule, the Commission will give due consideration to related regulatory reviews and permitting approvals as pertinent to the proposed transmission line, if the transmission line has already been acknowledged or approved by regulatory or permitting authorities.
(3) In the event a CPCN is granted, the certificate shall expire 15 years from date of issuance, except that a certificate shall expire 10 years from the date of issuance if construction has not commenced during those 10 years. Upon written request of a petitioner, the Commission may grant an extension on the term of a certificate for good cause shown. A request must be served on the service list for the associated CPCN docket, and if applicable, the docket for the petitioner's last acknowledged integrated resource plan.
Statutory/Other Authority: ORS 183, ORS 756 & ORS 758
Statutes/Other Implemented: ORS 758.015