Section 860-023-0161 - Major Event Filing by Electric Companies
Current through Register Vol. 63, No. 9, September 1, 2024
For any major event for which the CAIDI for the reliability reporting area exceeds five hours, the electric company must submit a report to the Commission within 30 business days after the conclusion of the event that includes:
(1) A description of the major event, the interruption causes, and factors that impacted restoration of service;
(2) The reliability reporting area and geographic area impacted;
(3) The total number of customers affected and the number of customers without service at periodic intervals; and
(4) The calculated SAIDI, SAIFI and CAIDI impacts (i.e., "Event SAIDI, SAIFI, and CAIDI") associated with the Major Event to customers on a reliability reporting area and a system-wide basis.
(5) This rule is effective beginning January 1, 2012.
Stat. Auth.: ORS 183, 756 & 757
Stats. Implemented: ORS 757.020