Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 23 - SERVICE STANDARDS
Section 860-023-0161 - Major Event Filing by Electric Companies

Universal Citation: OR Admin Rules 860-023-0161

Current through Register Vol. 63, No. 9, September 1, 2024

For any major event for which the CAIDI for the reliability reporting area exceeds five hours, the electric company must submit a report to the Commission within 30 business days after the conclusion of the event that includes:

(1) A description of the major event, the interruption causes, and factors that impacted restoration of service;

(2) The reliability reporting area and geographic area impacted;

(3) The total number of customers affected and the number of customers without service at periodic intervals; and

(4) The calculated SAIDI, SAIFI and CAIDI impacts (i.e., "Event SAIDI, SAIFI, and CAIDI") associated with the Major Event to customers on a reliability reporting area and a system-wide basis.

(5) This rule is effective beginning January 1, 2012.

Stat. Auth.: ORS 183, 756 & 757

Stats. Implemented: ORS 757.020

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.