Section 860-023-0091 - Electric Service Continuity

Universal Citation: OR Admin Rules 860-023-0091

Current through Register Vol. 63, No. 9, September 1, 2024

(1) An electric company must use reasonable means in design, operation, and maintenance to ensure reliable service to each customer. Such means include, but are not limited to, programs to minimize service interruptions.

(2) An electric company must have documented programs to maintain appropriate reliability levels.

(3) When an interruption occurs, each electric company must reestablish service with the shortest possible delay consistent with the safety of its employees, customers, and the public.

(4) An electric company must have recordkeeping systems in place to determine, and track interruptions, facilitate interruption restoration, and collect and analyze interruption data.

(5) This rule is effective beginning January 1, 2012.

Stat. Auth.: ORS 183, 756 & 757

Stats. Implemented: ORS 757.020

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.