Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 21 - UTILITY REGULATION
Section 860-021-0125 - Due and Payable Period

Universal Citation: OR Admin Rules 860-021-0125

Current through Register Vol. 63, No. 9, September 1, 2024

(1) Each energy or large telecommunications utility shall establish procedures to ensure that the period from the billing transmittal for all current charges, including payment for final bills, to the due date is not less than 15 days.

(2) If the bill is delivered by US mail, the due and payable period begins the day after the US Postal Service postmark or the day after the date of postage metering.

Stat. Auth.: ORS 183, 756, 757 & 759

Stats. Implemented: ORS 756.040

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.