Oregon Administrative Rules
Chapter 860 - PUBLIC UTILITY COMMISSION
Division 21 - UTILITY REGULATION
Section 860-021-0057 - Connection of Residential Energy Utility Service

Universal Citation: OR Admin Rules 860-021-0057

Current through Register Vol. 63, No. 9, September 1, 2024

(1) This rule applies to the connection of energy service for an applicant or customer who has satisfied the requirements of all applicable rules and regulations, and requested connection. This rule applies for connection at a location with existing service facilities where the utility need only activate service, or after any necessary line extension, construction or repair work has been completed.

(2) Each energy utility must provide a means by which an applicant or customer may contact the utility on a Business Day so that the applicant or customer may pay applicable charges, submit any necessary credit information and request connection of service. For purposes of this rule, Business Day is defined as Monday through Friday, 8:00 a.m. to 5:00 p.m., excluding state- or utility-recognized holidays.

(3) An energy utility must connect service as soon as reasonably possible, within the normal course of business, after an applicant or customer has satisfied the requirements for and requested connection. At a minimum, service must be connected within two Business Days, except as provided in section (4) of this rule.

(4) This section only applies to a natural gas service connection that is completed between September 15 and November 15 of each year, at an address where the applicant received service at any time during the past 12 months that was disconnected, but not reconnected within 20 days. Service must be connected as soon as reasonably possible, within the normal course of business, after an applicant or customer has satisfied the requirements for and requested connection. At a minimum:

(a) Service must be connected within two (2) Business Days when the applicant's prior service at the address was disconnected from August 15 to November 15 of the current year.

(b) Service must be connected within five (5) Business Days when the applicant's prior service at the address was disconnected from November 16 of the previous year to August 14 of the current year.

(5) With Commission concurrence, the connection requirements under this rule may be temporarily waived for any cause not reasonably within the control of the utility including, but not limited to, the following:

(a) A documented Force Majeure event;

(b) An action or default by an applicant or other person outside of the utility's control, including a cancellation of the request made by the applicant or customer;

(c) Major events, such as storms or system outages;

(d) Safety-related issues that preclude the utility from connecting service;

(e) The applicant's facilities cannot be accessed due to circumstances beyond the utility's control;

(f) The utility's equipment or facilities prevent the reconnection from occurring; or

(g) When the Commission approves a waiver.

Stat. Auth.: ORS Ch. 183 & 756

Stats. Implemented: ORS 756.040

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.